Project : Lim Kwee Jin
Location: No. 3, Lorong Jarak Kanan.




 

Name(Desc)

Contact

Name(Desc)

Contact

Name(Desc)

Contact

Tony

016-2940 454

Tom Yeap (Windows)

019-6890 773

Amin (AMC Builder)

019-2888 839

Mak

016-5518 511

Dak (Electric)

012-4620 515

Asan (AMC Builder)

017-2577 275

Aaron (PLATO)

016-9211 636

Cheong (Plumbing)

012-2333 363

Najib (AMC Builder)

016-3080 425

Tom (PLATO)

017-2907 102

RAM (Cleaning)

016-6600 974

Alam Jadi (Dustbin)

012-3865 556

Jason

012-2291 021

Dak (CCTV)

012-2163 391

Edmond (Steel)

012-9759 936

 

 

Ah Kit (Air-Cond)

012-3783 332

Ateh (Drainage)

016-6951 259


 
Site Report




2012/12/31 (Mon):

Follow up:
1) To put an extra tube (2-3") from Guard House to the bungalow.
2) NLC Pest Control will do fogging on 04/01 (Friday, 9-10am)
3) To build a concrete slab to widen the gate entrance.
4) Need to clean up the front drainage frequently.

1)Weather:
3.30pm- 4.30pm raining


2)Daily Tasks:
- Sand arrived - 1 load
- Corner bead arrived - 20pkt
- Kapur arrived 4.30pm - 100pkt
- Tom took 1 set pool mosaic for sample
- Tony and Mak came to visit site

3)Order Material:
- Blue plastic to cover plaster.


4)Feedback/problem:
-
Drainage Ateh didn't come to work, said need to arrange tools transfer from OUG.
- Mak called Dak to complaint the socket installed is not correctly leveled.
- Mak asked to clean up some wood piece in a plastered wall (1st floor), Jason has inform Hassan about it.
- Mak instruct to make sure the sand area is clean to avoid rubbish mixed with sand. Jason has asked Hanif to
clean it up.

5)Work progress (as at 6pm):
-




2012/12/29 (Sat):

Follow up:
1) To put an extra tube (2-3") from Guard House to the bungalow.
2) NLC Pest Control will do fogging on 04/01 (Friday, 9-10am)


1)Weather:
No rain


2)Daily Tasks:
- Sand arrived 12.30pm - 1 load


3)Order Material:
- NIL


4)Feedback/problem:
- Drainage Ateh cannot make it today to start work, he personally informed Aaron.
- Master bedroom toilet leanter did wrong. Has inform Hassan to redo.
********photo************


5)Work progress (as at 4pm):
-




2012/12/28 (Fri):

Follow up:
1) To put an extra tube (2-3") from Guard House to the bungalow.
2) NLC Pest Control will do fogging on 04/01 (Friday, 9-10am)


1)Weather:
No rain


2)Daily Tasks:
- L
ay brick workers help install corner bead to speed up plastering job.
- Aircond job almost done, remaining need to wait for plumbing job to finish the water piping.

3)Order Material:
- Sand 1 load
- Corner bead - 20pkt

4)Feedback/problem:
-
Electrical work could not complete in time, expected done by 15 Jan


5)Work progress (as at 6pm):
-




2012/12/27 (Thu):

Follow up:
1) To put an extra tube (2-3") from Guard House to the bungalow.
2) NLC Pest Control will do fogging on 04/01 (Friday, 9-10am)
3) Electrical work start 10 Dec, expected finished by 28 Dec


1)Weather:
No rain


2)Daily Tasks:
*** Aaron give Jason RM1000 (cheque CIMB 000120) as petty cash.

- Ateh (drain) came, asking us to dig for the drainage, will start to work Saturday (29/12)
- Remind Mak again to order Walcrete, coz stock is running low.
- Sand arrived 10.30am - 1 load
- Hassan adding 2 workers to speed up plastering job.
- Hassan instruct lay brick workers to help install corner bead to speed up plastering job.

3)Order Material:
- Walcrete (reminder)
- Sand brick for drain


4)Feedback/problem:
- NIL


5)Work progress (as at 6pm):
-




2012/12/26 (Wed):

Follow up:
1) To put an extra tube (2-3") from Guard House to the bungalow.
2) NLC Pest Control will do fogging on 04/01 (Friday, 9-10am)
3) 2nd phase drainage work has rescheduled, expected start 2nd Jan, finished by 10 Jan
4) Electrical work start 10 Dec, expected finished by 28 Dec


1)Weather:
No rain


2)Daily Tasks:
- Steel structure start work.
- Call Ateh (drain) to meet tmr (27/12) to discuss 2nd phase drainage work.
- Lightweight brick arrived - 12pm


3)Order Material:
- NIL


4)Feedback/problem:
- Steel structure contractor want to work late till 8pm, but we couldn't allowed.
Tom suggest they can do job without noise, till 7.30 but their car must park inside after 6pm.
- Aircond not working today but Ah Kit promised will finished job by this week.

5)Work progress (as at 6pm):
-




2012/12/25 (Tue): Christmas Off

Follow up:
1)


1)Weather:
pm- pm raining


2)Daily Tasks:
-


3)Order Material:
-


4)Feedback/problem:
-


5)Work progress (as at 6pm):
-




2012/12/24 (Mon):

Follow up:
1) To put an extra tube (2-3") from Guard House to the bungalow.
2) NLC Pest Control will do fogging on 04/01 (Friday, 9-10am)
3) 2nd phase drainage work has rescheduled, expected start 2nd Jan, finished by 10 Jan
4) Electrical work start 10 Dec, expected finished by 28 Dec
5) Need to add one concrete pole at 2nd floor.


1)Weather:
1.30pm- 3pm raining


2)Daily Tasks:
- Jason call Mak to send a hacking machine for workers to hack some area as instruct by Tom.


3)Order Material:
- Sand - 1load
- Walcrete - 400pkt


4)Feedback/problem:
-
Plumbing work has decided to change contractor, expected finished by 21 Jan
- Sam inform steel structure work can only start 26 Dec, expected finished by 15 Jan

5)Work progress (as at 6pm):
-




2012/12/21 (Fri) & 22 (Sat): (Jason OFF)

Follow up:
1)


1)Weather:
pm- pm raining


2)Daily Tasks:
-


3)Order Material:
-


4)Feedback/problem:
-


5)Work progress (as at 6pm):
-




2012/12/20 (Thu):

Follow up:
1) To put an extra tube (2-3") from Guard House to the bungalow.
2) NLC Pest Control will do fogging 21/12 & 04/01 (both Friday, 9-10am)
3) 2nd phase drainage work has rescheduled, expected start 2nd Jan, finished by 10 Jan
4) Electrical work start 10 Dec, expected finished by 28 Dec
5) Steel structure work start 20 Dec, expected finished by 15 Jan
6) Plumbing work expected finished by 28 Dec
7) Need to add one concrete pole at 2nd floor.


1)Weather:
2.30pm- 3.15pm raining


2)Daily Tasks:
- Steel structure material arrived 3.30pm. Finished unload 5pm


3)Order Material:
- NIL


4)Feedback/problem:
- Driver that deliver steel material said the supplier should arrange crane to unload.
Instead, they arrange 4 manpower to unload.


5)Work progress (as at 6pm):
-




2012/12/19 (Wed):

Follow up:
1) To put an extra tube (2-3") from Guard House to the bungalow.
2) NLC Pest Control will do fogging 21/12 & 04/01 (both Friday, 9-10am)
3) 2nd phase drainage work has rescheduled, expected start 2nd Jan, finished by 10 Jan
4) Electrical work start 10 Dec, expected finished by 28 Dec
5) Steel structure work start 20 Dec, expected finished by 15 Jan
6) Plumbing work expected finished by 28 Dec
7) Need to add one concrete pole at 2nd floor.


1)Weather:
9pm- 6pm no rain


2)Daily Tasks:
- Alam Jadi 3.30pm collect back their final dustbin. Paid cash, no more outstanding payment.
- Order lorry to transfer wood to No. 17 on 20/12


3)Order Material:
- Order dustbin


4)Feedback/problem:
- NIL


5)Work progress (as at 6pm):
-




2012/12/18 (Tue):

Follow up:
1) To put an extra tube (2-3") from Guard House to the bungalow.
2) NLC Pest Control will do fogging 21/12 & 04/01 (both Friday, 9-10am)
3) 2nd phase drainage work has rescheduled, expected start 2nd Jan, finished by 10 Jan
4) Electrical work start 10 Dec, expected finished by 28 Dec
5) Steel structure work start 20 Dec, expected finished by 15 Jan
6) Plumbing work expected finished by 28 Dec
7) Need to add one concrete pole at 2nd floor.


1)Weather:
5pm raining


2)Daily Tasks:
- Red bricks arrived 2pm & 4.30pm
- Sam (steel) came 1.30pm to visit site
- Called Tom Yeap to come & do measuring for sub-frame


3)Order Material:
- NIL


4)Feedback/problem:
- NIL


5)Work progress (as at 6pm):
-




2012/12/17 (Mon):

Follow up:
1) To put an extra tube (2-3") from Guard House to the bungalow.
2) NLC Pest Control will do fogging 21/12 & 04/01 (both Friday, 9-10am)
3) 2nd phase drainage work has rescheduled, expected start 2nd Jan, finished by 10 Jan
4) Electrical work start 10 Dec, expected finished by 28 Dec
5) Steel structure work start 20 Dec, expected finished by 15 Jan
6) Plumbing work expected finished by 28 Dec
7) Need to add one concrete pole at 2nd floor.


1)Weather:
3pm- 3.30pm; 5pm raining


2)Daily Tasks:
- Lorry arrived 10am, leave 4.30pm
- Tractor arrived 10am, leave 1.30pm
- Transfer used wood to No 17.


3)Order Material:
- Red-bricks (6 pallet)


4)Feedback/problem:
- DBKL officer come again to check cleanliness & mosquito issue.
This time nothing's wrong, but he still asked for money.
Tom paid RM100 to him.


5)Work progress (as at 6pm):
-





2012/12/15 (Sat):

Follow up:
1) To put an extra tube (2-3") from Guard House to the bungalow.
2) NLC Pest Control will do fogging 21/12 & 04/01 (both Friday, 9-10am)
3) 2nd phase drainage work start 17 Dec, expected finished by 10 Jan
4) Electrical work start 10 Dec, expected finished by 28 Dec
5) Steel structure work start 20 Dec, expected finished by 15 Jan
6) Plumbing work expected finished by 28 Dec
7) Need to add one concrete pole at 2nd floor.


1)Weather:
9am- 10am raining


2)Daily Tasks:
- Hassan buy 2pkt adhesive cement for lightweight brick wall - RM30
- Hacking job instruct by Tom


3)Order Material:
- NIL


4)Feedback/problem:
- NIL


5)Work progress (as at 6pm):
- Swimming pool



***********************************


2012/12/14 (Fri):

Follow up:
1) To put an extra tube (2-3") from Guard House to the bungalow.
2) NLC Pest Control will do fogging 21/12 & 04/01 (both Friday, 9-10am)
3) 2nd phase drainage work start 17 Dec, expected finished by 10 Jan
4) Electrical work start 10 Dec, expected finished by 28 Dec
5) Steel structure work start 20 Dec, expected finished by 15 Jan
6) Plumbing work expected finished by 28 Dec
7) Need to add one concrete pole at 2nd floor.


1)Weather:
3pm- 4pm raining


2)Daily Tasks:
*** Aaron gave RM500 petty cash to Jason
- 10.30am send workers to clean up No. 17
- 10.45am plumbing comes to work
- 1pm Mr Lee (swimming pool) comes visit site
- Sand arrived 2.30pm - 1 load
- Kapur (100pkt) & 3-in-1premixed cement (10pkt) arrived 3.45pm


3)Order Material:
- NIL


4)Feedback/problem:
- Mr Sam said steel structure work can only start 20/12. Jason has informed Tom.


5)Work progress (as at 6pm):
- Ground floor plaster



- 1st floor brick-wall



- Ground floor electrical


- No. 17 cleanup



***************************************


2012/12/13 (Thu):

Follow up:
1) To put an extra tube (2-3") from Guard House to the bungalow.
2) NLC Pest Control will do fogging 21/12 & 04/01 (both Friday, 9-10am)
3) 2nd phase drainage work start 17 Dec, expected finished by 10 Jan
4) Electrical work start 10 Dec, expected finished by 28 Dec
5) Steel structure work start 13 Dec, expected finished by 30 Dec
6) Plumbing work expected finished by 28 Dec
7) Need to add one concrete pole at 2nd floor.


1)Weather:
4pm- 6pm raining


2)Daily Tasks:
- Electrical (Dak) staffs came to work 8am

- Aircong staffs came to work 10.45am
- Red-brick arrived 10am - 4pallet (1 more pallet to be delivered later)
- Y10 steel arrived 1pm

3)Order Material:
- 3-in-1 cement - 10pkt
- Kapur - 100pkt
- Y10 steel - 20pcs


4)Feedback/problem:
- Dak (CCTV) not coming to work as scheduled, due to changed of order. Will come next Mon or Tue.


5)Work progress (as at 6pm):
- Ground floor electrical



- Ground floor air-cond


- Ground floor plaster


- 1st floor brick-wall


- 2nd floor open concrete-slab wood



*****************************************


2012/12/12 (Wed):

Follow up:
1) To put an extra tube (2-3") from Guard House to the bungalow.
2) NLC Pest Control will do fogging 21/12 & 04/01 (both Friday, 9-10am)
3) Mak ask Jason to get No.17 key from Aaron, then send workers to clean up for putting used wood.
4) 2nd phase drainage work start 17 Dec, expected finished by 10 Jan
5) Electrical work start 10 Dec, expected finished by 28 Dec
6) Steel structure work start 13 Dec, expected finished by 30 Dec
7) Plumbing work expected finished by 28 Dec
8) Need to add one concrete pole at 2nd floor.


1)Weather:
2pm- 4pm raining


2)Daily Tasks:
- Jason visit to No.17 Jalan D'sara Endah. Planning for cleaning work



3)Order Material:
- Ordered sand - 1 load


4)Feedback/problem:
- Mak informed red-bricks cannot be delivered today, due to supplier delivery problem.
Jason suggest to order at least 2 pallet with alternate supplier.
- Water plumbing workers not working today. Jason call the supervisor (Ah Sun), he said busy some other places.
Jason reported to Tom due to worried of delays of plumbing work. Tom consider change to other contractor.


5)Work progress (as at 6pm):
- First floor brick-wall


- Ground floor plaster




- Ground floor plaster
****************************************


2012/12/11 (Tue):

Follow up:
1) To put an extra tube (2-3") from Guard House to the bungalow.
2) NLC Pest Control will do fogging 21/12 & 04/01 (both Friday, 9-10am)
3) Mak ask Jason to get No.17 key from Aaron, then send workers to clean up for putting used wood.
4) 2nd phase drainage work start 17 Dec, expected finished by 10 Jan
5) Electrical work start 10 Dec, expected finished by 28 Dec
6) Steel structure work start 13 Dec, expected finished by 30 Dec
7) Plumbing work expected finished by 28 Dec
8) Need to add one concrete pole at 2nd floor.


1)Weather:
1pm- 3pm; 4pm-6pm raining


2)Daily Tasks:
- Sand arrived 10am - 1 load
- En Fahmi came 10.30am to check on the "honey-comb" beam. He will feed back to his boss for further action.
(refer to 26/11 report)
- Aircond Ah Kit & staff come to work 10.45am
- Plumbing Ah Sun & staff come to work 12.45pm
- Windows Tom Yeap
& staff come to install sub-frame 3pm


3)Order Material:
- NIL


4)Feedback/problem:
- Amin advised that, 1st floor lightweight brick structure might be too heavy. Tom has discuss with Amin to get a
solution.




5)Work progress (as at 6pm):
- Swimming pool


- Plumbing (manhole)


- Ground floor plaster


- Aircond piping


- Sub-frame



******************************************


2012/12/10 (Mon):

Follow up:
1) To put an extra tube (2-3") from Guard House to the bungalow.
2) NLC Pest Control will do fogging 21/12 & 04/01 (both Friday, 9-10am)
3) Mak ask Jason to get No.17 key from Aaron, then send workers to clean up for putting used wood.
4) 2nd phase drainage work start 17 Dec, expected finished by 10 Jan
5) Electrical work start 10 Dec, expected finished by 28 Dec
6) Steel structure work start 13 Dec, expected finished by 30 Dec
7) Plumbing work expected finished by 28 Dec
8) Need to add one concrete pole at 2nd floor.


1)Weather:
9am-6pm no raining


2)Daily Tasks:
- Dustbin arrived 2pm


3)Ordered Material:
- Sand - 1 load
- Red brick - 5 pallets
- Mesh wire for brick wall - 5 rolls
*** Mak ask Jason to buy
(@ RM9/roll)


4)Feedback/problem:
- Both aircond & plumbing contractor cannot make it today, will come tomorrow.
- Hassan said lay brick workers will rest tomorrow due to red brick finished, and no delivery coz Tuesday is
Selangor holiday.


5)Work progress (as at 6pm):
- Swimming pool


- Ground floor plaster


- 1st floor brick-wall




*******************************************


2012/12/08 (Sat):

Follow up:
1) To put an extra tube (2-3") from Guard House to the bungalow.
2) Pest Master will do fogging on 10am, Friday (23/11) and every fortnight (7/12), (21/12), (04/01)
3) Mak ask Jason to get No.17 key from Aaron, then send workers to clean up for putting used wood.
4) 2nd phase drainage work start 17 Dec, expected finished by 10 Jan
5) Electrical work start 10 Dec, expected finished by 28 Dec
6) Steel structure work start 13 Dec, expected finished by 30 Dec
7) Plumbing work expected finished by 28 Dec
8) Need to add one concrete pole at 2nd floor.


1)Weather:
9am- 4pm no raining


2)Daily Tasks:
- Today start plaster job. Total 4 workers doing plaster.
- Lorry came to collect 2 machines in front.



3)Order Material:
- NIL


4)Feedback/problem:
- Alam Jadi said lorry broke down, so can only send dustbin on 10/12 (Mon)


5)Work progress (as at 6pm):
- Ground floor plaster:


- 1st floor brick-wall



- Swimming pool



****************************************


2012/12/07 (Fri):

Follow up:
1) To put an extra tube (2-3") from Guard House to the bungalow.
2) Pest Master will do fogging on 10am, Friday (23/11) and every fortnight (7/12), (21/12), (04/01)
3) Mak ask Jason to get No.17 key from Aaron, then send workers to clean up for putting used wood.
4) 2nd phase drainage work start 17 Dec, expected finished by 10 Jan
5) Electrical work start 10 Dec, expected finished by 28 Dec
6) Steel structure work start 10 Dec, expected finished by 30 Dec
7) Plumbing work expected finished by 28 Dec
8) Need to add one concrete pole at 2nd floor.


1)Weather:
5.30pm start raining


2)Daily Tasks:
- Sand (1 load) arrived 11am
- Edmond (steel) brought contractor to visit site 11am
- Tom Yeap and workers start install sub-frame 11.15am
- Fogging job 9.30am - 10.15am (by NLC Pest Control - RM200/job)



3)Order Material:
- NIL


4)Feedback/problem:
- En Fahmi called to confirm repairing "honey comb" beam. Said will call Jason again on Monday to confirm
repairing date.
- Edmond said steel structure work can only start 13/12 (Thu) as they can only start order material on Monday.
(already inform Tom)


5)Work progress (as at 6pm):
- 1st floor brick-wall



- 2nd floor open up slab wood


- Ground floor install sub-frame (not completed, to be continue on Monday)




*******************************************


2012/12/06 (Thu):

Follow up:
1) To put an extra tube (2-3") from Guard House to the bungalow.
2) Pest Master will do fogging on 10am, Friday (23/11) and every fortnight (7/12), (21/12), (04/01)
3) Mak ask Jason to get No.17 key from Aaron, then send workers to clean up for putting used wood.
4) 2nd phase drainage work start 17 Dec, expected finished by 10 Jan
5) Electrical work start 10 Dec, expected finished by 28 Dec
6) Steel structure work start 10 Dec, expected finished by 30 Dec
7) Plumbing work expected finished by 28 Dec
8) Need to add one concrete pole at 2nd floor.


1)Weather:
3pm- 4.30pm raining


2)Daily Tasks:
- Crane arrived 9.50am, leave 3.15pm
- Lightweight bricks arrived 10.15am
- Concrete (3 lorry) arrived 11.30am, 1pm & 2.50pm
- Edmond came by 2.30pm to meet Tom.
-
Informed Dak (electric) can start to work. He will come on 11/12 (Tue)
- Tom Yeap said sub-frame will only start install tomorrow (7/12)
- PVC corner bead arrived 12.30pm



3)Order Material:
- ordered dustbin


4)Feedback/problem:
- Swimming pool workers not coming today.
- Tom informed Hassan about changes for brick-wall plan in master bedroom, and also add one concrete pole
at first floor.
- Concrete reduced from 17(m3) to 14(m3), so Amin approved to pay RM10 to compensate the 3rd lorry driver,
for only delivered 2(m3).
- Hassan let workers stop working @4pm due to no rest (for concrete job) & working under rain.


5)Work progress (as at 5pm):
- 1st floor brick-wall


- 1st floor master bedroom concrete


- ground floor putting up PVC corner bead



*****************************************


2012/12/05 (Wed):

Follow up:
1) Call Dak (electric) when the plan is ready. Waiting for Tom's instruction.
2) Pest Master will do fogging on 10am, Friday (23/11) and every fortnight (7/12), (21/12), (04/01)
3) Tom Yeap inform they will only start install "sub-frame" on Thursday (6th Dec)
4) 2nd phase drainage work start 17 Dec, expected finished by 10 Jan
5) Electrical work start 10 Dec, expected finished by 28 Dec
6) Steel structure work start 10 Dec, expected finished by 30 Dec
7) Plumbing work expected finished by 28 Dec
8) Mak ask Jason to get No.17 key from Aaron, then send workers to clean up for putting used wood.
9) To put an extra tube (2-3") from Guard House to the bungalow

1)Weather:
12.30pm - 2.30pm raining;
5.30pm start raining


2)Daily Tasks:
- Lightweight bricks arrived 10.30am
- 2.30pm Dak (CCTV) came to visit site, asked us to put an extra tube (2-3") from Guard House to the banglo.
- 3pm Edmond (Steel) came to visit site,
has called Tom for some clarification.
- 5.45pm supplier send 5bags of PVC corner bead. Said the rest to be delivered on 6/12 (Thu)

3)Order Material:
- Order one more pallet (90pcs) of lightweight bricks
- Order 2 loads of sand


4)Feedback/problem:
- Mak informed that crane broke down and cannot make it today. So concrete work postpone to 6/12 (Thu).
- Workers has extend their hostel for plaster workers to stay.


5)Work progress (as at 6pm):
- ground floor brick-wall


- 1st floor brick-wall


- swimming pool (and cleaning job around)



**************************************


2012/12/04 (Tue):

Follow up:
1) Call Dak (electric) when the plan is ready. Waiting for Tom's instruction.
2) Pest Master will do fogging on 10am, Friday (23/11) and every fortnight (7/12), (21/12), (04/01)
3) Tom Yeap inform they will only start install "sub-frame" on Thursday (6th Dec)
4) 2nd phase drainage work start 17 Dec, expected finished by 10 Jan
5) Electrical work start 10 Dec, expected finished by 28 Dec
6)
Steel structure work start 10 Dec, expected finished by 30 Dec
7) Plumbing work expected finished by 28 Dec


1)Weather:
2.30pm start raining


2)Daily Tasks:
Task given Tom & Aaron gave a few task to follow up:
i) Call Ateh to touch up drain
* Ateh promise will touch up, but to do it when they come for the following drainage work.

ii) make sure maid room windows are ready for sub frame
* Hassan promised will get it done.

iii) 1st floor wall (facing pool) have changes, inform Hassan
* has informed Hassan & Amin. They estimated 1 pallet (aprox 80-90pcs) lightweight bricks needed.

iv) Call NLC pest control & neighbor to arrange Friday fogging
* En Azam said no need to do their house. However he is appreciate we took the necessary action.
* NLC (David) charge us RM200 per job, but COD.
* Fogging will be done on Friday (7/12) 9am.

v) Push Hassan to redo the "mistaken wall"
* Hassan promised will do this two day

vi) Call Cheong (plumbing) to push speed up work
* Cheong said they are busy this week at other site, will come next week.

vii) Inform Dak (CCTV), Ah Kit (Air-cond) & Edmond (steel structure) to start work on 10/12 (Mon)
* Called all of them. They will come visit the site first this week.

viii)
Bank in cheque for PestMaster
* Already call to get their bank account no, will bank in when pass by Public Bank.

i
x) clean up area around swimming pool
* Had instruct Hanif to start doing it.

- Bricks arrived 1pm
- Mosaic (pool) arrived 4pm


3)Order Material:
- Ordered with Mak lightweight bricks - 1 pallet (80-90pcs)


4)Feedback/problem:
- NIL


5)Work progress (as at 6pm):
- 1st floor brick-wall



****************************************


2012/12/03 (Mon):

Follow up:
1) Call Dak (electric) when the plan is ready. Waiting for Tom's instruction.
2) Pest Master will do fogging on 10am, Friday (23/11) and every fortnight (7/12), (21/12), (04/01)
3) Tom Yeap inform they will only start install "sub-frame" on Thursday (6th Dec)


1)Weather:
- 4.15pm start raining


2)Daily Tasks:
*** Aaron gave RM500 petty cash to Jason
*** Issue salary cheque for Jason


3)Order Material:
- NIL


4)Feedback/problem:
- Tom & Aaron gave a few task to follow up:
i) Call Ateh to touch up drain
ii) make sure maid room windows are ready for sub frame
iii) 1st floor wall (facing pool) have changes, inform Hassan
iv) Call NLC pest control & neighbor to arrange Friday fogging
v) Push Hassan to redo the "mistaken wall"
vi) Call Cheong (plumbing) to push speed up work
vii) Inform Dak (CCTV), Ah Kit (Air-cond) & Edmond (steel structure) to start work on 10/12 (Mon)
viii) Record RAM's workers working days

ix) Bank in cheque for PestMaster
x) clean up area around swimming pool

5)Work progress (as at 6pm):
- 1st floor brick-wall



**************************************


2012/12/01 (Sat):

Follow up:
1) Dak (electric) when the plan is ready. Waiting for Tom's instruction.
2) Pest Master will do fogging on 10am, Friday (23/11) and every fortnight (7/12), (21/12), (04/01)
3) Will start install "sub-frame" next Monday (3rd Dec)


1)Weather:
1.30pm- 2.30pm & 4pm-6pm raining


2)Daily Tasks:
*** Aaron gave RM400 to Hassan for Alam Jadi payment

- Cement (50pkt) arrived 3.30pm
- Walcrete (400pkt) arrived 4pm, but it's raining, 6pm only start unloading.


3)Order Material:
- NIL


4)Feedback/problem:
- Walcrete delivery using 40ft lorry, can't parked into site premises.
Hassan asked his workers to help move
the neighbor's dustbin (even it's raining), so lorry can stop aside without blocking the road.
Jason appreciates his initiative




- The lorry driver request extra money to unload the walcrete for longer distance, Simon (the supplier) agreed
to pay them RM350, asked Jason to pay first and he will bank in the money to Jason.


5)Work progress (as at 6pm):
- 1st floor brick-wall



***********************************


2012/11/30 (Fri):

Follow up:
1) Dak (electric) when the plan is ready. Waiting for Tom's instruction.
2) Pest Master will do fogging on 10am, Friday (23/11) and every fortnight (7/12), (21/12), (04/01)
3) Will start install "sub-frame" next Monday (3rd Dec)


1)Weather:
3.30pm start raining


2)Daily Tasks:
- Cheong's workers came 9.30am for plumbing work.

- Sand arrived 2pm
- Door frame arrived 3pm, total 13pcs

3)Order Material:
- Mak ordered 400pkt of Walcrete, waiting for supplier to arrange delivery
- Ordered dustbin

4)Feedback/problem:
- NIL


5)Work progress (as at 6pm):
- 1st floor brick-wall




***************************************


2012/11/29 (Thu):

Follow up:
1) Dak (electric) when the plan is ready. Waiting for Tom's instruction.
2) Pest Master will do fogging on 10am, Friday (23/11) and every fortnight (7/12), (21/12), (04/01)
3) Will start install "sub-frame" next Monday (3rd Dec)



1)Weather:
3.15pm- 4pm raining


2)Daily Tasks:
- Engineer Mr Liew came by 11.30am to look at the honey comb concrete. Said need to redo the 2 beam.
(pls refer to 26/11 report)


3)Order Material:
- ordered with Mak 1 load of sand.


4)Feedback/problem:
- 4pm even rain has stopped, no one work for 2nd floor slab.
Act: Will talk to Amin abt this.


5)Work progress (as at 6pm):
- 1st floor brick-wall


****************************************


2012/11/28 (Wed):

Follow up:
1) Dak (electric) when the plan is ready. Waiting for Tom's instruction.
2) Pest Master will do fogging on 10am, Friday (23/11) and every fortnight (7/12), (21/12), (04/01)
3) Will start install "sub-frame" next Monday (3rd Dec)

1)Weather:
- 5pm start raining


2)Daily Tasks:
- NIL



3)Order Material:
- NIL


4)Feedback/problem:
- Amin said IF ONLY no raining at all, then 2nd floor concrete slab "maybe" can done by Saturday.


5)Work progress (as at 6pm):
- 1st floor brick-wall


- 2nd floor slab


****************************************


2012/11/27 (Tue):

Follow up:
1) Call Dak (electric) when the plan is ready. Waiting for Tom's instruction.
2) Pest Master will do fogging on 10am, Friday (23/11) and every fortnight (7/12), (21/12), (04/01)



1)Weather:
5.30pm start raining


2)Daily Tasks:
- Put Abate to stagnant water area.



- Window supplier (Tom Yeap) came to do final measuring. Will start install "sub-frame" next Monday (3rd Dec)

- Tony has agree with Ateh for additional drainage work with total amount RM2000, but we have to responsible for digging job first.


3)Order Material:
- NIL


4)Feedback/problem:
- Najib told Jason Amin said "no need" to redo the mistaken brick-wall (see pic). Jason has report to Tom about this.
Tom will deal with Amin directly.




5)Work progress (as at 6pm):
- Ground floor brick-wall


- First floor open concrete slab



*****************************************



2012/11/26 (Mon):


Follow up:
1) Call Thomas (windows) & Dak (electric) when ground floor brick-wall is done.
2) Pest Master will do fogging on 10am, Friday (23/11) and every fortnight (7/12), (21/12), (04/01)



1)Weather:
3pm-6pm raining


2)Daily Tasks:
- Najib not coming in today, send car for repair.

- Dustbin arrived 1pm

- Brian bring a few friend (buyer) to visit site, no complain.
But unfortunately the strong wind has blown down the "zinc gate", fell on his car, causing a 6" scratch on the hood.
Jason apology to Brian, he said is ok.
(
"zinc gate" that fell)




3)Order Material:
- NIL



4)Feedback/problem:
- Tom found some problem with 1st floor concrete slab. Has taken photos and send to engineer.


-Jason instruct to clean up some area, found out a missing part need to be hacked. Will inform Mak's workers when they come.



5)Work progress (as at 6pm):
- Ground floor brick-wall












2012/11/24 (Sat):

## Today Jason work from 12pm-4.30pm


Follow up:
1) Call Thomas (windows) & Dak (electric) when ground floor brick-wall is done.
2) Pest Master will do fogging on 10am, Friday (23/11) and every fortnight (7/12), (21/12), (04/01)



1)Weather:
9am-6pm no raining


2)Daily Tasks:
- Crane arrived 9.50am leaved 6.45pm
Moved bricks to 2nd floor while waiting for concrete.
Finished late beacuse Najib need crane to move steels to 2nd floor.


- Concrete arrived 12.50pm, leaved 3.15pm

- 1st floor stairs concrete done by 2.50pm



3)Order Material:
- ordered dustbin to be delivered on 26/11 (Mon)


4)Feedback/problem:
- Concrete arrived 12.50pm but 1st floor stairs not yet ready. (see pics) Called Amin but cannot get thru.
Mak instruct Jason to pay RM10 to the driver as compensate the 40mins waiting time.

***Jason didn't know how's the stairs should be ready by the time concrete.
Act: Will learn from experience and check to confirm in future.
Will tell Amin to communicate well with his workers in future, as his supervisor Najib also complained
that concrete shouldn't be ordered when the job is not ready.

(progress as at 6pm @ 23/11)
(only ready by 1.20pm @ 24/11)



5)Work progress (as at 4.30pm):
- Hacking job


-Pool


- Brick wall




*************************************

2012/11/23 (Fri):

Follow up:
1) Call Thomas (windows) & Dak (electric) when ground floor brickwall is done.
2) Pest Master will do fogging on 10am, Friday (23/11) and every fortnight (7/12), (21/12), (04/01)



1)Weather:
1.30pm-2.30pm raining


2)Daily Tasks:
- Dustbin arrive 10.30am

- Fogging 11am - 11.20am


-Kapur (100pkt) arrived 1.30pm




3)Order Material:
- Amin said he will buy 400pcs PVC angle beads (as shown in pic), price @ RM2.xx/pcs. Already informed Tom.




4)Feedback/problem:
- Ateh (drainage worker's supervisor) claimed that their Bosch grinder (see sample pic) had lost yesterday when
he want to collect back.

Act: Jason asked Amin/Asan & Mak's staff (hacking workers), they said they didn't know about it.
Jason told Ateh since he didn't assigned anyone at the site to look after the grinder, and there's no prove
that the grinder was on the site, Jason can only ask all the workers to take note and inform Jason should
anyone sees the grinder in future.
(Sample pic: Bosch grinder)


- there's a mistake on one of the brick wall (see pic). Asan should built a concrete beam first then only the brick.
Act: Tom had inform Asan to rectify it.




5)Work progress (as at 6pm):
- Hacking job






- Pool



- Drainage



- ground floor brick wall










***************************************

2012/11/22 (Thu):

## Today Jason work from 10.30am - 6pm

Follow up:
1) Call Thomas (windows) & Dak (electric) when ground floor brickwall is done.
2) Ask neighbor's to move their dustbin to clear the way, for the next crane.
3) Pest Master will do fogging on 10am, Friday (23/11) and every fortnight (7/12), (21/12), (04/01)



1)Weather:
3pm-5pm raining


2)Daily Tasks:
- Landlord (Eugene & Brian) came by 2.30pm. They looks satisfied with the progress & site condition.

- Jason instruct 2 wooden dustbin to be built, to improve site cleanliness



3)Order Material:
- Ordered with Mak

"kapur" (100pkt)

- Jason order dustbin


4)Feedback/problem:
- Hacking workers only hack the "pump house" for pool. They start to rest after raining @ 3pm.
Jason asked to hack plaster ceiling but they said continue tmr, because the dustbin filled up too quickly.


5)Work progress (as at 6pm):
- Hacking job



- Pool


- Ground floor brick wall




*****************************************

2012/11/21 (Wed):

## Today Jason work from 2.00pm - 6.30pm

Follow up:
1) Call Thomas (windows) & Dak (electric) when ground floor brick wall is done.
2) Ask neighbor's to move their dustbin to clear the way, for the next crane.
3) Pest Master will do fogging on 10am, Friday (23/11) and every fortnight (7/12), (21/12), (04/01)



1)Weather:
9am - 6pm no rain

2)Daily Tasks:
- Amin added 2 more workers for brick wall.

- Hacking & pool job continue.

- Dustbin arrived 10am

- Bricks arrived 12pm (10 pallets)


3)Order Material:

Ordered with Mak
- 2.5" wood nail, 2" concrete nail

- handbarrow's wheel for replacement



4)Feedback/problem:
-Amin want to order concrete & crane for 1st floor stairs & moving bricks to 2nd floor, by Saturday.
Jason let Amin order with Mak.


5)Work progress (as at 6pm):
- Hacking job


- Swimming Pool


- Brick wall (ground floor):



-First Floor (stairs & open concrete slab)



***************************************

2012/11/20 (Tue):

Follow up:
1) Call Thomas (windows) & Dak (electric) when ground floor brickwall is done.
2) Ask neighbor's to move their dustbin to clear the way, for the next crane.
3) Pest Master will do fogging on 10am, Friday (23/11) and every fortnight (7/12), (21/12), (04/01)


1)Weather:
9am - 6pm no rain


2)Daily Tasks:
- Mak send people to do hacking & pool job

- Cheong (plumbing) meeting with Tom, said need to apply permit to hack the road for reallocate the water meter.

- Sand (1 load) & Cement (50 pkt) both arrived 11.15am

- Drainage work progress well.

- Asan said DBKL officer got bring people to do fogging at our site around 8am

- Tom prepared a letter for neighbor (En Azam) rgd mosquito & water leaking issue. Jason drop into letter box 5pm.



3)Order Material:
- NIL


4)Feedback/problem:
- Dustbin & bricks cannot make it, will come tomorrow.

- Brick wall no progress today, as Asan rather wait for bricks to arrive tmr than to get bricks from 1st floor.
Instead, brick wall workers building beams as shown in photos below:




5)Work progress (as at 6pm):
- Drainage system
& clearing side walk


- Hacking job

(rubbish not clear because dustbin delayed. To be cleared tmr)

- Pool



*****************************************

2012/11/19 (Mon):

Follow up:
1) Call Thomas (windows) & Dak (electric) when ground floor brickwall is done.
2) Meeting with Cheong (plumbing) on 20/11 (Tue)
3) Ask neighbor's to move their dustbin to clear the way, for the next crane.



1)Weather:
9am - 3pm raining

2)Daily Tasks:

- Called Cheong (water plumbing) to set up meeting, on 20/11 (Tue) 10am.

- Mak will arrange hacking work only on Tuesday due to raining.

- Tom talked to Amin to add 2 more workers to speed up ground floor brick wall progress.
Target to complete by Thursday.


3)Order Material:
- Mak inform he had order the following to be delivered on 20/11 (Tue):
i) sand - 1 load
ii) red brick - 10 pallet
iii) cement - 50pkt

- Jason order dustbin to be delivered on 20/11 (Tue)


4)Feedback/problem:

- Site no electricity since Sunday 5pm.
Act: Mak send ppl to check. Fixed around 3pm. (cause: switch box cable loosen)

- Drainage workers didn't come to work due to raining.

- DBKL (En Ramli) came, said neighbor complained about mosquitoes. Found some mosquitoes near poolside
and want to give compound. Tom approved to settle on the spot.
Act: En Ramli instruct to put chemical (ABETE) or small fish in the pool to kill mosquitoes.
Tom has called pest control Pest Master to quote price for spray & supply chemicals.


-
DBKL (En Ramli) also advised to take care of rubbish & septic tank system.
Act: Tom will plan for further action.
Jason has instruct RAM to setup small dustbins and prioritized solving the stagnant water issue daily.



5)Work progress (as at 6.30pm):
- Ground floor brick wall


**************************************

2012/11/17 (Sat):

Jason OFF

3)Order Material:
- Called Mak to order sand, to be delivered on Monday. As request by Asan.


************************************

2012/11/16 (Fri):

Follow up:
1) Call Thomas (windows) & Dak (electric) when ground floor brickwall is done.
2) Call Cheong (water plumbing) on 19 Nov (Mon) to set up meeting.
3) Tom instruct call Mak to hack floor & plaster on Monday.
4) Ask neighbor's to move their dustbin to clear the way, for the next crane.



1)Weather:
9am - 6pm no rain

2)Daily Tasks:

- Crane arrived 10am

- 1st concrete arrived 11.15am

- 2nd concrete arrived 12pm, waited 1 hour for 1st concrete & bricks to unload.

- 3rd concrete arrived 1.15pm, waited 45min

- 4th concrete arrived 3pm; 5th concrete arrived 4.15pm; 6th concrete arrived 4.30pm

- Crane leaved 6.40pm




- Bricks lorry arrived 11.30am, waited 1 hour for first concrete to finished unload.
(Asan instruct 4 pallet located on ground floor, 6 pallet located on 1st floor.)




- Cover back the gap for drainage work as instruct by Tom


3)Order Material:
- NIL


4)Feedback/problem:
- Called to postpone dustbin delivery to Saturday due to crane & concrete lorry are blocking the passage.
Act: Instruct cleaning workers to temporary compile rubbish in certain location.


- Have to buy lunch for crane operator, budget around RM10

- A few concrete lorry drivers asked money for "minum teh", Jason refused to pay,
Act: Jason bought "100 Plus" for them when buying lunch for "crane operator"
(please advise if need to pay)

- Road was too narrow for the crane to move in & out the site. Almost breaks neighbor's tree & electric cable.
Act: Jason will asked neighbor's to move their dustbin to clear the way, for the next crane.


- Still slow on ground floor brick wall progress.
Act: Jason asked Asan to push faster.

**(Progress as at 6.30pm 16/11/2012)


*****************************************

2012/11/14 (Wed):

Follow up:
1) Call Thomas (windows) & Dak (electric) when ground floor brickwall is done.
2) Call Cheong (water plumbing) on 19 Nov (Mon) to set up meeting



1)Weather:
9am - 6pm no rain
 
2)Daily Tasks:
- Tom bought tape for setting up perimeter for parking.
* Act: Asked Najib to tied up.


- Tong sampah almost full.
* Act: Called @3pm to order. Deliver on Friday

3)Order Material:
- Confirmed with Mak Concrete & bricks will be delivered on Friday.

4)Sub-con & Supplier's feedback/problem
- 10am all workers rest for abt 30mins
- 2pm 2 workers sleep on the desk for abt 20mins
* Act: Take note
 
- Sand delivery driver don't know our location, still need Jason to go out and lead.
* Act: Will ask supplier try to arrange same driver that know our loc.
 
- 3 person assigned for brickwall, 1 moving bricks & 2 building walls. Jason think the progress is a bit slow.
* Will monitor for one more day (Friday) before talk to Asan / Amin.






 
 




































=Template=

2012/11/26 (Mon):

Follow up:
1)


1)Weather:
pm- pm raining


2)Daily Tasks:
-


3)Order Material:
-


4)Feedback/problem:
-


5)Work progress (as at 6pm):
-



=Template=